Purchase Order Date and Due Date
Hi
I have entered my current open purchases with suppliers for items I will receive in the future via the purchase order system.
When entering a purchase order there is only one date to enter which is the order date.
I have been entering the date the item is due to be released to me.
This is perfect as I can use the report system to sort by month and get a total balance for each month and know how much I will be spending.
The issues start though when I create a customer invoice for an item on purchase order. My store sells items not yet released quite often and takes a monthly payment from the customer until item is released.
If the item is on a purchase order dated 31.12.2018 as it's released december 2018 then I am not able to do an invoice dated todays date 25.05.18 for the item as I get an error message saying the invoice date is before the date I started tracking the item.
The only solution is to change the purchase order date to a date before the invoice date.
When viewing the purchase order summary screen though, it shows 2 dates.

A date and a due date column. There's no ability to add a date and also a due date to a purchase order though when creating one.
This would suggest the date is the date the purchase order was placed with the supplier and the due date would be the expected arrival date ?
It seems a little restrictive that you can only add a single date being the date the order was placed as that means I have no ability to view by due date which would be incredibly useful and how I planned on using the system.
Why are there 2 date columns and yet no ability to enter 2 different dates?
I thought I would use the memo and type December 2018 for example so I know when the items are due but there's no report based on the memo content so no way of actually producing reports based on when a PO is physically due to get a summary cost per month :(